Project Profile – The extension and redevelopment of Terminal 2 including works to the link and pier areas.
Our Works – Installation of floor screeds on Piers 1 and 2, as well as all screeding works on the Terminal 2 extension which had doubled in size upon completion.
Throughout this project we’ve installed over 80,000sqm of CPG Europe products including 70,000sqm of Flowcrete Fast-K Screed and 15,000 bags of Flowcrete Industrial Top.
Over 13,200 tonnes of sand, 160,000 bags of cement, and 7,000 man-days were required to complete this state-of-the-art terminal that will provide a host of amenities and security for millions of passengers each year.